News Flash

City News & Events

Posted on: March 22, 2021

FDOT UPDATE: 95 Express Phase 3 Tubular Marker Installation Activity to Cause Traffic Impact

The Florida Department of Transportation (FDOT), District Four, is pleased to provide an activity update for 95 Express Phase 3 between Cypress Creek Road and Glades Road within Broward and Palm Beach counties as part of the South Florida Managed Lanes Network.

PROJECT ACTIVITY UPDATE

As part of the $1 billion 95 Express Phase 3 initiative, FDOT will be installing the final lift of asphalt, adding pavement markings for future managed lane ingress/egress points and installing white tubular markers along I-95 from north of Cypress Creek Road to south of Glades Road to delineate the future managed lanes from the general use lanes.  95 Express Phase 3 in Broward and Palm Beach counties will extend the existing Phase 1 & 2 systems currently in use in Miami-Dade County to provide a safe and efficient commute for South Florida’s tri-county area. Once the tubular makers are installed, the Department will begin calibration of Intelligent Transportation System (ITS) devices between Cypress Creek Road and Glades Road. Commissioning of the managed express lanes between Cypress Creek Road and Glades Road is anticipated to begin this summer. Once authorized, overhead signs will advise drivers of the entry and exit points, along with the SunPass all-electronic toll amounts. Construction of the 95 Express Phase 3 project commenced in Broward County in August 2016. 95 Express Phase 3A-2, from Commercial Boulevard to SW 10th Street, was completed in October 2019, and 95 Express Phase 3B-1, from SW 10th Street to south of Glades Road, is anticipated to be completed this summer. Phase 3C, from Hollywood Boulevard to Broward Boulevard, Phase 3A-1, from Broward Boulevard to Commercial Boulevard, and Phase 3B-2, from Glades Road to Linton Boulevard, are currently under construction.

TRAFFIC IMPACT

  • Lane closures on I-95 are permitted nightly 9:30 PM until 5:30 AM, Sunday through Thursday.
  • One lane on I-95 may close at 9:30 PM, multiple lanes may close at 10:30 PM. All lanes will reopen by 5:30 AM.

WEEKEND TRAFFIC IMPACT

  • Weekend lane closures on I-95 are permitted 11:00 PM, Friday night through 5:00 AM, Monday morning.
  • Weekend work will begin on March 26, 2021, and continue each weekend until completed for the exception of April 2—4, where there will be no weekend work.

Constr Map

CONTACT INFORMATION

William Grey, P.E., FDOT Project Manager

william.grey@dot.state.fl.us or (954) 540-0062

Aurelio Matos, P.E., Consultant Sr. Project Engineer

amatos@chperez.com or (305) 323-1462

Andrea Pacini, I-95 Community Outreach Specialist

apacini@corradino.com or (954) 299-6561